Economic Order Quantity Calculation for Rockne's Restaurant

How can Rockne's Restaurant minimize their cost for ordering napkins?

Given data: Rockne's Restaurant currently uses 7300 boxes of napkins each year. The cost to order the boxes of napkins is $21 per order and the annual carrying cost for one box is $1.

Calculation for Economic Order Quantity:

To minimize the cost of ordering napkins, Rockne's Restaurant can utilize the Economic Order Quantity (EOQ) formula.

The EOQ formula is given by:

EOQ = sqrt((2 * D * S) / H)

Where:

  • EOQ is the Economic Order Quantity
  • D is the annual demand (number of boxes used per year)
  • S is the ordering cost per order
  • H is the carrying cost per box per year

Given values:

  • Annual demand (D) = 7300 boxes
  • Ordering cost per order (S) = $21
  • Carrying cost per box per year (H) = $1

Substitute the values into the EOQ formula:

EOQ = sqrt((2 * 7300 * 21) / 1) = sqrt(306600) ≈ 554.08

Therefore, Rockne's Restaurant should order approximately 554 boxes of napkins at a time to minimize cost.